Scope of Works: Enabling earthworks for full site including roads, carparks, building and sports pitches
Constraints: The excavated materials from this green field site were marginal and required careful management and treatment by the addition of quicklime to provide the required formations of 5% CBR to externals and 150Kn/m2 within the building, with maximum settlement of 10mm on 600mm plate.
Achievements:
Due to RJT Excavations’ early involvement in the design process, we were able to value engineer the earthworks to give a balancing cut/fill volume which eliminated the requirement to remove surplus materials from site
Project Details
Client
Morrison Construction
Value
£520,000
Duration
April 2016 (10weeks)
Referee
Project Manager: Mick Hill
Overview –Phase 1 of the works involved the temporary excavation to allow the construction of a new water treatment…
Scope of Works: Contract Crushing provider, load and haul. Constraints: SEPA Licensing, Production targets, achieving technical gradings, Supervision and labour…
Scope of Works: The extension of an existing substation requiring construction of a new 60,000m2 platform along with associated road…
Overview Reduced level excavation/filling of existing greenbelt site for proposed housing development consisting of 44 units, infrastructure and environmental management. Scope of Works,…
Overview – Initially contracted to construct 650m long access road into proposed Energy from Waste Facility. Works involved cut/fill of…
Scope of Works: Foundations, RC floor slabs, RC retaining walls, Drainage and SUDS retention scheme, Hard landscaping to new Primary…
Scope of Works: earthworks, foundations, floor slabs, drainage, services and hard landscaping. Constraints: The excavated materials from this green…
RJT undertook the earthworks element of the golf course construction including all topsoil stripping and storage, cut fill for fairways…
Scope of Works: The works consisted of the construction of a new 1.6km length of single lane 7.3m wide carriageway…
Scope of Works: Breaking out existing PQ concrete, Lean mix concrete on existing stands and asphalt on existing LIMA taxiway,…