Our Services
Home > Profile > Earthworks > Dunbar Energy from Waste Facility
Dunbar Energy from Waste Facility







Overview – Initially contracted to construct 650m long access road into proposed Energy from Waste Facility. Works involved cut/fill of made ground (previous infilled quarry), lime improvement of embankment fill to engineers specification and stone import capping works. Follow on works consisted of cut/fill works for the building platform/piling mat works and the installation of 750mm imported stone piling mat.
Scope of Works, Achievements and Constraints
60,000m3 earthworks cut/fill with lime improvement to road embankment
- 60,000m3 cut/fill within piling mat/platform works.
- 30,000m3 of stone import to road capping and piling platforms
- Dust suppression and surface water management
Project Details
Client
Viridor / PC - Land Engineering
Value
£0.85M
Duration
April 2014 (22weeks)
Referee
Referee: Senior Project Manager: Joe Mclaughlin
Referee: Commercial: Danny McInnes
Overview –Phase 1 of the works involved the temporary excavation to allow the construction of a new water treatment…
Scope of Works: Contract Crushing provider, load and haul. Constraints: SEPA Licensing, Production targets, achieving technical gradings, Supervision and labour…
Scope of Works: The extension of an existing substation requiring construction of a new 60,000m2 platform along with associated road…
Overview Reduced level excavation/filling of existing greenbelt site for proposed housing development consisting of 44 units, infrastructure and environmental management. Scope of Works,…
Scope of Works: Foundations, RC floor slabs, RC retaining walls, Drainage and SUDS retention scheme, Hard landscaping to new Primary…
Scope of Works: earthworks, foundations, floor slabs, drainage, services and hard landscaping. Constraints: The excavated materials from this green…
RJT undertook the earthworks element of the golf course construction including all topsoil stripping and storage, cut fill for fairways…
Scope of Works: The works consisted of the construction of a new 1.6km length of single lane 7.3m wide carriageway…
Scope of Works: Breaking out existing PQ concrete, Lean mix concrete on existing stands and asphalt on existing LIMA taxiway,…
Scope of Works: Enabling earthworks for full site including roads, carparks, building and sports pitches Constraints: The excavated materials…