RJT undertook the earthworks element of the golf course construction including all topsoil stripping and storage, cut fill for fairways greens and tee’s, shaping works to greens, tee’s and bunkers. Excavation to form large water features, stone revetment to existing bodies of water. Import, crush and provide a settled formation for building plots within areas of water
Topsoil Strip 100,000m3, Cut/Fill Fairway Shaping 250,000m3, Stone Import 16,000m3, Re-soiling 440,000 m2
Contractor design and manage an environmental plan to ensure compliance with SEPA regulations, planning conditions and control of silt to surrounding environment.
Working closely with Archaeologist and archaeological features using relevant techniques to satisfy restrictions.
Interpretation of Architects requirements and aspirations for the look and playability of the course.
Project Details
Client
Land Engineering/South Lanarkshire Council
Value
£5.0M
Duration
May 2016 (28weeks)
Referee
Technical Referee: Ronald Lindsay