











Overview
Reduced level excavation/filling of existing greenbelt site for proposed housing development consisting of 44 units, infrastructure and environmental management.
Scope of Works, Achievements and Constraints
- All works carried out as principle contractor.
- Contractor design to manage environmental plan to ensure compliance with SEPA regulations.
- Testing for suitability of soils for compliance with specification.
- Handling peat off site.
- Blasting existing rock outcrops within built up area.
- Process crushing and using as podium fill
- Construct phase 1&2 roads and drainage as part of the works.
- 15,000m3 topsoil strip
- 60,000m3 cut (rock blasted, process and use as fill)
- 45,000m3 peat removal off site
- Groundwork’s and drainage installation
Project Details
Client
CALA Homes
Value
£2.4M
Duration
May 2014 ( 38weeks)
Referee
Referee Project: Angus Murray
Referee Commercial: Jamie Johnston
Overview –Phase 1 of the works involved the temporary excavation to allow the construction of a new water treatment…
Scope of Works: Contract Crushing provider, load and haul. Constraints: SEPA Licensing, Production targets, achieving technical gradings, Supervision and labour…
Scope of Works: The extension of an existing substation requiring construction of a new 60,000m2 platform along with associated road…
Overview – Initially contracted to construct 650m long access road into proposed Energy from Waste Facility. Works involved cut/fill of…
Scope of Works: Foundations, RC floor slabs, RC retaining walls, Drainage and SUDS retention scheme, Hard landscaping to new Primary…
Scope of Works: earthworks, foundations, floor slabs, drainage, services and hard landscaping. Constraints: The excavated materials from this green…
RJT undertook the earthworks element of the golf course construction including all topsoil stripping and storage, cut fill for fairways…
Scope of Works: The works consisted of the construction of a new 1.6km length of single lane 7.3m wide carriageway…
Scope of Works: Breaking out existing PQ concrete, Lean mix concrete on existing stands and asphalt on existing LIMA taxiway,…
Scope of Works: Enabling earthworks for full site including roads, carparks, building and sports pitches Constraints: The excavated materials…