Our Services

Denny North Substation

Scope of Works: The extension of an existing substation requiring construction of a new 60,000m2 platform along with associated road works and drainage. 

Constraints: The platform is partially constructed within an existing raided peat bog. RJT excavations worked with the principle contractor to develop a peat management plan which enabled most of the excavated peat to remain on site.

Many elements of the construction work have been undertaken adjacent existing transmission pylons and under live overhead cables.

As an alternative to disposal off site of soft clay arising’s, RJT Excavations processed these materials using lime stabilisation techniques in order to render suitable for use in platform construction.

 

Achievements:

  • Excavation of 110,000m3 pf peat
  • Re-use of 80,000m3 of peat on site using methods designed to promote the regeneration of existing bogs and wetlands covering an area of 150,000m2
  • Installation and removal of 4,000m temporary floating roads
  • Processing 70,000m3 of unsuitable materials using the addition of lime to provide structural fills
  • Placement of 60,000m3 of imported granular fills to create the platform surface
  • Installation of pipe-work and RC structure for platform and access roads drainage systems.

Project Details

Client

Balfour Beatty Civil Engineering

Value

£2M

Duration

April 2016 (10weeks)

Referee

Referee - Technical: Andy Gardner

Referee - Commercial:  Ross Macdonald

Related Project Profiles

View all projects